Project Gallery 10: Asbestos Abatement & Restoration Home Previous Next
Project Location: Bechtel Elementarty School, Camp McTureous, Okinawa
Customer: U.S. Army Corps of Engineer, Engineer District, Okinawa Page 1 of 2
Safety and Quality Control meeting..
Plastic sheeting installed on the stairways prior to removal of existing floor covering that contained asbestos.
USACE's prescribed construction signboard.
GTR Robert Ishiara (extreme right) stressing an
important point prior to the asbestos removal work.
Asbestos workers donning protective paraphernalia
just before starting removal work..
Installed overhead is an air monitoring/sampling device.
HEPA Exhaust Air Filtering Equipment
USACE's Inspector doing preparatory phase inspection
Carpentry workers installing asbestos control area prior to removal of existing asbestos containing carpets
Door and entrance lockouts to prevent unauthorized people from entering asbestos abatement areas
Carpet-substrate areas shown after asbestos removal and prior to collapsing plastic sheeting